Temporary Best Management Practices (BMPs) are often among the last items addressed during site cleanup. Silt fence, inlet protection, wattles, and other temporary controls eventually need to be removed, and our last blog discussed things to consider before removing.
In this blog, we will discuss five common BMP removal mistakes to watch for and how to avoid them.
1. Removing Inlet Protection Too Soon
One common mistake is removing storm drain inlet protection as soon as the surrounding area appears finished. While nearby landscaping or paving may be complete, other areas of the project could still be under construction. Runoff from those areas can carry sediment toward nearby inlets, even if the immediate area around the drain is stabilized.
Removing inlet protection before contributing drainage areas are adequately stabilized can allow sediment and construction debris to enter the storm drain system.
How to avoid it: Before removing inlet protection, evaluate the entire drainage area contributing runoff to the inlet. Confirm that upstream construction activities are complete, exposed areas are stabilized, and additional sediment controls are no longer necessary.
2. Removing Silt Fence Before Surrounding Areas Are Stabilized
Silt fence is commonly installed along site perimeters, drainage boundaries, and other locations where sediment-laden runoff needs to be contained.
As construction progresses, contractors may begin removing sections of silt fence in areas where work has been completed. However, if nearby disturbed areas remain exposed, removing those controls can create an opportunity for sediment to move beyond the construction limits.
How to avoid it: Evaluate the conditions on both sides of the silt fence before removal. Consider nearby slopes, exposed soil, drainage patterns, and ongoing construction activities. Keep controls in place where they are still needed to prevent sediment from leaving the site.
3. Assuming Newly Seeded Areas Are Fully Stabilized
Applying seed is an important step in establishing vegetation, but it does not mean an area is immediately stabilized.
Newly seeded soil can remain vulnerable to rainfall and runoff while vegetation is developing. Without adequate coverage, soil particles can still become detached and transported during storm events.
How to avoid it: Verify that the area meets applicable final stabilization requirements before removing controls that protect it. Under Colorado’s COR400000 construction stormwater permit, final stabilization generally requires uniform vegetative cover with an individual plant density of at least 70% of pre-disturbance levels, or equivalent permanent alternative stabilization methods.
Seeding, mulching, or applying an erosion control blanket may be part of the stabilization process, but the actual site conditions determine whether stabilization requirements have been met.
4. Leaving Accumulated Sediment Behind
BMP removal involves more than simply pulling stakes, removing fabric, or taking out a filter sock. Temporary controls often collect sediment over time. If that accumulated material is left behind, rainfall and runoff can move it into nearby drainage systems or other areas of the site.
For example, removing a sediment-filled silt fence without first addressing the material collected along its length can redistribute the very sediment the BMP was installed to contain.
How to avoid it: Remove accumulated sediment and construction debris before or during BMP removal. Dispose of or stabilize the material appropriately so it cannot be transported by future runoff. Also inspect the area after removal and restore any disturbed soil as needed.
5. Forgetting to Update the SWMP
A construction site changes throughout the project, and the SWMP should reflect those changes. As temporary controls are removed, replaced, or relocated, the plan may no longer accurately represent what is installed in the field. This can create confusion during inspections and make it difficult to determine whether the site is following its intended stormwater management approach.
Outdated BMP locations or descriptions can also make it harder for contractors and inspectors to identify which controls are still required.
How to avoid it: Update the SWMP as BMPs are removed or modified. Make sure the documentation reflects current site conditions, control locations, and any changes to the stormwater management approach. Keep supporting records as required by the applicable permit.
BMP Removal Is Part of Stormwater Compliance
Temporary BMP removal is an important part of construction closeout, but it should not be treated as an afterthought.
Taking the time to evaluate site conditions, address accumulated sediment, and update the SWMP helps prevent unnecessary compliance issues during the final stages of construction.